TenneT awards Next Geosolutions with route survey contracts
Team Sea and Coast | 29/06/2020

TenneT TSO B.V., the system operator, has picked Next Geosolutionsfor a contract to carry out cable route surveys on three wind zones in the Dutch North Sea.

The company has also signed a backup agreement with Fugro for the work.

Here are some specifics for the agreement:

  • Next Geosolutions will carry out cable route surveys on the 700 MW HollandseKust (west) Beta, the 700 MW Ten noorden van de Waddeneilanden, and the 4 GW IJmuiden Ver zones.
  • The agreement does not include the unexploded ordnance (UXO) surveys.
  • The 700 MW HollandseKust (west) Alpha zone is not covered by the agreement.

These zones were identified by the Dutch government in the Offshore Wind Energy Roadmap 2030. The Offshore Wind Energy Roadmap 2030 sets out plans for the development of additional 7 GW of offshore wind capacity in the Dutch North Sea between 2024 and 2030.

Tenders for the new wind farm zones will be opened from 2021 onward, starting with the HollandseKust (west).

The HollandseKust (west) Beta will be commissioned in 2025, while Ten Noorden van de Waddeneilanden will be online the following year.

The Dutch government will issue two tenders for the permits to develop the IJmuiden Ver sites, in 2023 for IJmuiden Ver I and II and in 2025 for IJmuiden Ver III and IV. TenneT will construct two 2 GW offshore platforms with grid connections in the IJmuiden Ver zone.